Sunday, April 26, 2009

Further progress




This week two main things were finished: the room Treille (the wall in stucco veneziano was polished and the others finished) and the installation of the staircase.

Another important work started in midweek, i.e. the groundworks for the garden and the road to the parking area. Unfortunately rain stopped this after two days and perhaps for half of next week too.

Tuesday, April 14, 2009

Month of March

A good progress was made in March: all the coffrages in the bedrooms, the living room and the toilets were made. The false ceiling in the living room was done with clear poplar wood, parquet style. The stairwell was prepared and painted in an yellow enduit papier maché. In the room Treille on the ground floor the wall received a terra cotta colour, technique stucco veneziano (Venetian Plaster).